Skip to main content

I30 Mobility Task Force

Construction News: Updated July 9, 2008

Dates may change due to weather or other conditions and events.

Also see the press release page.

Major Traffic Impacts Anticipated for Next Three Months

  • Northbound FM 157/Collins Street traffic will be moved onto the existing southbound bridge.  The reconfiguration will accommodate two through lanes in each direction and a left turn lane onto eastbound Copeland Road.
  • Temporary closure of I-30 eastbound entrance at Nolan Ryan Expressway. Alternate entrance ramp available at Convention Center Dr. Anticipate restoration of ramp access in spring 2009.
  • Permanent closure of I-30 eastbound exit for Ballpark Way. Alternate exit ramp available at Nolan Ryan Expressway.

 

Week of July 14, 2008

  • Prepare Center Street bridge deck.
  • Place permanent concrete pavement on eastbound mainlanes near Ballpark Way overpass.
  • Place permanent concrete pavement on eastbound frontage road between Cooper Street and Center Street.
  • Switch FM 157/Collins Street traffic to west bridge and begin preparation for demolition of east bridge.
  • Continue pavement reconstruction of Wet-N-Wild Way western section.
  • Place asphalt pavement on westbound frontage road approaching FM 157/Collins Street.
  • Begin preparation for temporary I-30 eastbound exit to Nolan Ryan Expressway.
  • Continue substructure work for Baird Farm Road bridge and median ramp.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of July 7, 2008

  • Prepare Center Street bridge deck.
  • Place permanent concrete pavement on eastbound mainlanes near Ballpark Way overpass.
  • Continue pavement reconstruction of Wet-N-Wild Way western section.
  • Place asphalt pavement on westbound frontage road approaching FM 157/Collins Street.
  • Continue substructure work for Baird Farm Road bridge and median ramp.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of June 30, 2008

  • Continue placing Center Street bridge decking.
  • Portion of Wet-N-Wild Way closed to traffic from FM 157/Collins Street for pavement reconstruction.
  • Portion of Ryan Plaza closed to traffic for pavement reconstruction.
  • Place asphalt pavement on westbound frontage road approaching FM 157/Collins Street.
  • Place permanent concrete pavement on eastbound frontage road from Cooper Street towards Center Street extension.
  • Continue substructure work for Baird Farm Road bridge and median ramp.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of June 23, 2008

  • Set partial fourth and final fiifth spans of bridge beams for the Center Street extention and continue placing decking.
  • Continue embankment for westbound frontage road leading to FM 157/Collins Street.
  • Continue substructure work for Baird Farm Road bridge and median ramp.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of June 16, 2008

  • Set third and partial fourth spans of bridge beams for the Center Street extention and continue placing decking.
  • Continue Center Street bridge structure work.
  • Continue embankment for westbound frontage road leading to FM 157/Collins Street.
  • Continue substructure work for Baird Farm Road bridge and median ramp.
  • Continue installing drainage system. I-30 esatbound entrance ramp from Cooper Street closed and re-opened..
  • Continue retaining wall and temporary shoring work throughout project site.
  • Prepare esatbound frontage road from Cooper Street towards Center Street and eastbound mainlanes near Ballpark Way overpass for permanent contrete pavement

Week of June 9, 2008

  • Set second span of bridge beams for the Center Street extension and continue placing decking.
  • Continue Center Street bridge structure work.
  • Restore Industrial Court.
  • Prepare embankment for westbound frontage road leading to FM 157/Collins Street.
  • Continue substructure work for Baird Farm Road bridge and median ramp.
  • Continue installing drainage system. Night activity crossing FM 157/Collins Street.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of June 2, 2008

  • Continue placing Center Street bridge decking.
  • Continue Center Street bridge structure work.
  • Continue preparing eastbound frontage road from Cooper Street to west of Center Street extenstion.
  • Continue soil stabilization for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Continue substructure work for Baird Farm Road bridge and median ramp.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of May 26, 2008

  • Continue placing Center Street bridge decking.
  • Continue Center Street bridge structure work.
  • Begin soil stabilization for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Prepare eastbound frontage road from Cooper Street to west of Center Street extenstion.
  • Continue substructure work for Baird Farm Road median ramp.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of May 19, 2008

  • Set first span of bridge beams for the Center Street extension and begin placing decking.
  • Continue Center Street bridge structure work.
  • Begin soil stabilization for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Continue excavation for temporary I-30 westbound entrance ramp from FM 157/Collins Street.
  • Continue substructure work for Baird Farm Road median ramp.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of May 12, 2008

  • Complete excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Begin substructure work for Baird Farm Road median ramp.
  • Begin excavation for temporary I-30 westbound entrance ramp from FM 157/Collins Street.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue Center Street bridge structure work.

Week of May 5, 2008

  • Continue excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue Center Street bridge structure work.
  • Switch traffic to new I-30 westbound exit ramp for FM 157/Collins Street the evening of Tuesday, April 15.

Week of April 28, 2008

  • Continue crushing concrete and excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way. Includes night excavation from April 15 through April 24.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue Center Street bridge structure work.
  • Temporarily close I-30 eastbound entrance ramp at Cooper Street on Saturday, May 3 for pavement demolition.

Week of April 21, 2008

  • Continue crushing concrete and excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way. Includes night excavation.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue Center Street bridge structure work.

Week of April 14, 2008

  • Continue crushing concrete and excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way. Includes night excavation from April 15 through April 24.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue Center Street bridge structure work.
  • Switch traffic to new I-30 westbound exit ramp for FM 157/Collins Street the evening of Tuesday, April 15.

Week of April 7, 2008

  • Continue pavement demolition and excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue Center Street bridge structure work.

Week of March 31, 2008

  • Continue pavement demolition and excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Continue installing drainage system.
  • Continue retaining wall and temporary shoring work throughout project site.

Week of March 24, 2008

  • Complete first major I-30 traffic switch to north side of I-30.
  • Begin pavement demolition and excavation work for future I-30 eastbound mainlanes from Nolan Ryan Expressway to Ballpark Way.
  • Continue installing drainage system.
  • Complete restoration of I-30 eastbound entrance ramp at Copeland Rd/Convention Center Dr intersection
  • Continue retaining wall and temporary shoring work throughout project site.

Week of March 17, 2008

  • Continue installing drainage system.
  • Complete I-30 westbound mainlane detour pavement.
  • Scheduled switch of I-30 westbound mainlane traffic to detour pavement for March 20.
  • Complete restoration of traffic island at Ballpark Way/Convention Center Dr intersection. Expect temporary work zone removed and traffic restored around March 22.
  • Continue restoration of I-30 eastbound entrance ramp at Copeland Rd/Convention Center Dr intersection.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue building temporary I-30 westbound exit for FM 157/Collins St.

Week of March 10, 2008

  • Continue installing drainage system.
  • Begin restoration of traffic island at Ballpark Way/Convention Center Dr intersection.
  • Begin restoration of I-30 eastbound entrance ramp at Copeland Rd/Convention Center Dr intersection.
  • Continue retaining wall and temporary shoring work throughout project site.
  • Continue building temporary I-30 westbound exit for FM 157/Collins St.